\chapter{Project Management} \section{Project Plan} \subsection{Initial Plan} \begin{sidewaysfigure} \begin{ganttchart}[ vgrid, hgrid, x unit=0.9cm, y unit chart=0.6cm, y unit title=0.6cm, % height of title line and gap title height=1 % use full height for title, leaving no gap ]{1}{18} \gantttitle{Project Plan}{18} \\ \gantttitlelist{1,...,18}{1} \\ \gantttitle{September}{2} \gantttitle{October}{4} \gantttitle{November}{5} \gantttitle{December}{4} \gantttitle{January}{3} \\ \ganttbar{Prepare Thesis Document}{1}{2} \\ \ganttbar{Create Project Plan}{1}{2} \\ \ganttbar{Research Other Solutions}{1}{2} \\ \ganttbar{Experiment with Hardware}{1}{2} \\ \ganttbar{Write Introduction}{2}{2} \\ \ganttbar{Define Use Cases \& Personas}{3}{3} \\ \ganttbar{Define Requirements}{3}{4} \\ \ganttbar{Plan Solution}{5}{6} \\ \ganttbar{Document Solution}{5}{6} \\ \ganttbar{Define Test Cases}{6}{6} \\ \ganttbar{Prepare Hardware for Prototype}{7}{7} \\ \ganttbar{Create Prototype for Sender}{7}{9} \\ \ganttbar{Create Prototype for Receiver}{8}{10} \\ \ganttbar{Testing}{11}{12} \\ \ganttbar{Benchmarking}{11}{12} \\ \ganttbar{Document Materials \& Methods}{13}{13} \\ \ganttbar{Document Future Work}{13}{13} \\ \ganttbar{Create Abstract}{14}{14} \\ \ganttbar{Create Poster}{14}{15} \\ \ganttbar{Create Movie}{16}{16} \\ \ganttbar{Finish Thesis Report}{16}{17} \\ \ganttbar{Prepare Presentations}{17}{18} \end{ganttchart} \caption{Project Plan} \end{sidewaysfigure} \subsection{Actual Plan} \begin{sidewaysfigure} \begin{ganttchart}[ vgrid, hgrid, x unit=0.9cm, y unit chart=0.6cm, y unit title=0.6cm, % height of title line and gap title height=1 % use full height for title, leaving no gap ]{1}{18} \gantttitle{Project Plan}{18} \\ \gantttitlelist{1,...,18}{1} \\ \gantttitle{September}{2} \gantttitle{October}{4} \gantttitle{November}{5} \gantttitle{December}{4} \gantttitle{January}{3} \\ \ganttbar{Prepare Thesis Document}{1}{2} \\ \ganttbar{Create Project Plan}{1}{2} \\ \ganttbar{Research Other Solutions}{1}{2} \\ \ganttbar{Experiment with Hardware}{1}{2} \\ \ganttbar{Write Introduction}{2}{2} \\ \ganttbar{Define Use Cases \& Personas}{3}{3} \\ \ganttbar{Define Requirements}{3}{4} \\ \ganttbar{Plan Solution}{5}{6} \\ \ganttbar{Document Solution}{5}{6} \\ \ganttbar{Define Test Cases}{6}{6} \\ \ganttbar{Prepare Hardware for Prototype}{7}{7} \\ \ganttbar{Create Prototype for Sender}{7}{9} \\ \ganttbar{Create Prototype for Receiver}{8}{10} \\ \ganttbar{Testing}{11}{12} \\ \ganttbar{Benchmarking}{11}{12} \\ \ganttbar{Document Materials \& Methods}{13}{13} \\ \ganttbar{Document Future Work}{13}{13} \\ \ganttbar{Create Abstract}{14}{14} \\ \ganttbar{Create Poster}{14}{15} \\ \ganttbar{Create Movie}{16}{16} \\ \ganttbar{Finish Thesis Report}{16}{17} \\ \ganttbar{Prepare Presentations}{17}{18} \end{ganttchart} \caption{Project Plan} \end{sidewaysfigure} // TODO: Actual plan // TODO: First subject: Speakers // TODO: Organization / Planning / Mockups / Experiments / Meetings / Sickness // TODO: problems / pain points / learnings